NWSC EXTENDS WATER TO OVER 341,000 PEOPLE IN GULU CITY ,SURROUNDING AREAS
By Our reporter
In Gulu
The Government of Uganda through the National Water and Sewerage Corporation (NWSC) is constructing the Gulu Water Supply and Sanitation project.
The project will serve over 341,000 people in Gulu, Karuma, Kamdini, Minakulu, Bobi, Palenga, Koro- Abili and the surrounding areas, drawing water from River Nile at Karuma.
The project encompasses; 72km bulk water transmission main from Karuma to Gulu, 30million litres per day capacity water intake at Karuma and 10million litres per day capacity Nile water treatment plant.
The project will have 5.3million litres capacity water reservoirs, Water Pumping station, 42 water borne toilets and Improve access to safe Sanitation to over 170, 000 people.
Work on the treatment plant, reservoirs and pipeline are expected to commence in June next year and will end by June 2023.
During a tour of the project, the managing director of NWSC Dr. Eng Silver Mugisha said that the corporation is working towards 100% water and sanitation for all residents of Gulu City.
“A few years back, our water source Oyitino dam and the taps in Gulu dried up as a result of the extreme weather conditions in the area. NWSC through GoU support and working with other development partners embarked on plans to boost water supply reliability in the area.” he said
Dr. Silver Mugisha said NWSC is working on both short- and long-term interventions. The short-term interventions already completed include; Upgraded Oyitino dam water storage capacity from 2.7B litres of water to now 4.2B litres of water, improved daily water production from 3million litres of water per day to now 10million litres of water supplied and rehabilitated the waste water stabilization ponds.
The others Constructed are Faecal sludge treatment plant at Cubu, upgraded existing sewers and laid new sewer mains in Gulu City and Upgraded the Oyitino dam pumping system from 5million litres of water pay capacity.